• Post-Replacement Procedure
1. Start the instrument.
Click here for "Starting the Instrument (TOC-1000e)"
2. Check the operation of the pump.
Click here for "Starting the Instrument (TOC-1000e)"
2. Check the operation of the pump.
[Maintenance] - [Mechanical Check] - [Standard Machine]

Select the stream for the pump valve(4).When you select a stream and hear the valve’s operating sound from the instrument, that is a sign of normal operation.
3. Set the pump operation time to 0.
1) Display the [Counter] screen.
Refer: "Checking the Replacement Timing"
2) Press
in the [Pump] row.
1) Display the [Counter] screen.
Refer: "Checking the Replacement Timing"
2) Press
3) Press [OK] on the confirmation screen.
The [Value] value is set to [0 Days].
4) Press [Back].
You will be returned to the Home screen.
The [Value] value is set to [0 Days].
4) Press [Back].
You will be returned to the Home screen.

4. To continue without replacing the reactor, perform rinsing, remove the bubbles, and then perform calibration.
1) Rinse the flow lines.
2) Check for bubbles.
Click here for "Rinsing the Flow Lines/Click here for Checking for Bubbles (TOC-1000e)"
3) Calibrate the instrument.
Click here for "Calibration (TOC-1000e)"
If you are replacing the reactor, perform the procedure from step 4 in "Replacing the Reactor".